Lab 1.1Scrum certifications, Chapter 1

Run one Scrum sprint for an IT team: backlog, planning, daily, review and retro

Level
Easy
60 min
Machines
a free board tool (GitHub Projects, Jira, Trello) or paper and sticky notes
Status
Not started

Goal

Use the Scrum framework from the SFC course on a real IT goal: "Move the company file server to a cloud file share without data loss". You write the product vision, user stories with acceptance criteria, estimate them, plan a 2-week sprint, simulate the daily stand-ups, and finish with a sprint review and a retrospective. A team of one (you playing all roles) is fine for the lab.

Before you start

  • A board with the columns Product Backlog, Sprint Backlog, In Progress, Done.
  • The roles (SBOK names): Product Owner (the IT manager), Scrum Master, Scrum Team (2 admins). The stakeholders are the department heads.

Tasks

  1. Write the project vision in one sentence and three measurable success criteria.
  2. Write 8 user stories in the form As a … I want … so that …, each with 2–3 acceptance criteria (Given/When/Then or a checklist). Include one technical story (for example backups) and one security story (permissions).
  3. Prioritise the backlog (MoSCoW or value/effort) and estimate each story in story points (1, 2, 3, 5, 8) with planning-poker reasoning.
  4. Define the Definition of Done for the team (5–7 points).
  5. Sprint planning: the team's velocity is 13 points. Choose the stories for a 2-week sprint and write the sprint goal.
  6. Simulate 3 daily stand-ups (the three questions) and one impediment that the Scrum Master removes.
  7. Sprint review: which stories meet the DoD? What do you show the stakeholders? What new items go into the backlog?
  8. Retrospective: start / stop / continue, and one improvement action for the next sprint with an owner.

Check your work

  • Every story has an As a / I want / so that line and testable acceptance criteria.
  • The sprint backlog adds up to 13 points or a little less, and matches the sprint goal.
  • The DoD is the same for every story (not one DoD per story).
  • The review shows only stories that are Done; unfinished work goes back to the product backlog.
  • The retro ends with a concrete, owned action — not just a list of complaints.

Hints

Show the hints
  • A good story is INVEST: independent, negotiable, valuable, estimable, small, testable.
  • If a story is 8 points or more, split it (for example by department or by file type).
  • The sprint length does not change during the sprint, and the sprint goal does not change either; scope inside it can be negotiated with the Product Owner.
  • In SODFC terms, operations work (incidents) still arrives during a sprint — keep a small buffer or a separate Kanban lane.

Solution

Show the solution
  1. Vision: "All departments use a secure cloud file share by 31 December, with no data loss and no more VPN for files." Success: 100 % of 1.2 TB migrated with checksums verified; 0 permission complaints after 2 weeks; old server switched off.
  2. and 3. The prioritised backlog (example):
    product-backlog.txt
    P1  (5)  As an admin I want a full inventory of shares, sizes and owners, so that we plan the migration.
             AC: list of all shares; size per share; one owner per share confirmed.
    P2  (3)  As security I want groups mapped to the new share permissions, so that nobody gets more access than today.
             AC: mapping table approved by each department head; no "Everyone" permissions.
    P3  (5)  As finance I want my folders moved first, so that the year-end close uses the new system.
             AC: all files copied; checksums equal; users can open and save files.
    P4  (2)  As an admin I want nightly backups of the cloud share, so that we can restore deleted files.
             AC: backup job runs; a test restore of one folder works.
    P5  (3)  As a user I want the share mapped automatically at login, so that I do not need help desk.
    P6  (5)  As HR I want my folders moved with restricted access, so that personal data stays private.
    P7  (2)  As help desk I want a one-page guide, so that we answer the first questions fast.
    P8  (3)  As the IT manager I want the old server read-only for 30 days, then off, so that we can roll back.
  3. Definition of Done: code/config in Git · peer-reviewed · acceptance criteria tested · backup covered · documentation updated · the Product Owner accepted it · no open critical security finding.
  4. Sprint 1 goal: "Finance works on the cloud share, safely." Sprint backlog: P1 (5) + P2 (3) + P3 (5) = 13 points.
  5. Daily stand-ups: Day 3 impediment — the cloud subscription lacks storage quota; the Scrum Master gets the quota raised by the cloud owner the same day.
  6. Review: P1 and P2 are Done; P3 is 90 % (two users cannot save Excel files due to a lock setting) → not Done, back to the backlog with a new bug story. Stakeholders see the live finance share and the permission table. New item: "Large CAD files sync slowly — test a sync client".
  7. Retro: start — pair on permission checks; stop — starting big copies during work hours; continue — daily checksum report. Action: Admin 2 schedules all copies after 20:00 from sprint 2.