Goal
Use the Scrum framework from the SFC course on a real IT goal: "Move the company file server to a cloud file share without data loss". You write the product vision, user stories with acceptance criteria, estimate them, plan a 2-week sprint, simulate the daily stand-ups, and finish with a sprint review and a retrospective. A team of one (you playing all roles) is fine for the lab.
Before you start
- A board with the columns Product Backlog, Sprint Backlog, In Progress, Done.
- The roles (SBOK names): Product Owner (the IT manager), Scrum Master, Scrum Team (2 admins). The stakeholders are the department heads.
Tasks
Tick a task when it is done. Only your browser remembers it.
- Write the project vision in one sentence and three measurable success criteria.
- Write 8 user stories in the form As a … I want … so that …, each with 2–3 acceptance criteria (Given/When/Then or a checklist). Include one technical story (for example backups) and one security story (permissions).
- Prioritise the backlog (MoSCoW or value/effort) and estimate each story in story points (1, 2, 3, 5, 8) with planning-poker reasoning.
- Define the Definition of Done for the team (5–7 points).
- Sprint planning: the team's velocity is 13 points. Choose the stories for a 2-week sprint and write the sprint goal.
- Simulate 3 daily stand-ups (the three questions) and one impediment that the Scrum Master removes.
- Sprint review: which stories meet the DoD? What do you show the stakeholders? What new items go into the backlog?
- Retrospective: start / stop / continue, and one improvement action for the next sprint with an owner.
Check your work
- Every story has an As a / I want / so that line and testable acceptance criteria.
- The sprint backlog adds up to 13 points or a little less, and matches the sprint goal.
- The DoD is the same for every story (not one DoD per story).
- The review shows only stories that are Done; unfinished work goes back to the product backlog.
- The retro ends with a concrete, owned action — not just a list of complaints.
Hints
Show the hints
- A good story is INVEST: independent, negotiable, valuable, estimable, small, testable.
- If a story is 8 points or more, split it (for example by department or by file type).
- The sprint length does not change during the sprint, and the sprint goal does not change either; scope inside it can be negotiated with the Product Owner.
- In SODFC terms, operations work (incidents) still arrives during a sprint — keep a small buffer or a separate Kanban lane.
Solution
Show the solution
- Vision: "All departments use a secure cloud file share by 31 December, with no data loss and no more VPN for files." Success: 100 % of 1.2 TB migrated with checksums verified; 0 permission complaints after 2 weeks; old server switched off.
- and 3. The prioritised backlog (example):product-backlog.txt
P1 (5) As an admin I want a full inventory of shares, sizes and owners, so that we plan the migration. AC: list of all shares; size per share; one owner per share confirmed. P2 (3) As security I want groups mapped to the new share permissions, so that nobody gets more access than today. AC: mapping table approved by each department head; no "Everyone" permissions. P3 (5) As finance I want my folders moved first, so that the year-end close uses the new system. AC: all files copied; checksums equal; users can open and save files. P4 (2) As an admin I want nightly backups of the cloud share, so that we can restore deleted files. AC: backup job runs; a test restore of one folder works. P5 (3) As a user I want the share mapped automatically at login, so that I do not need help desk. P6 (5) As HR I want my folders moved with restricted access, so that personal data stays private. P7 (2) As help desk I want a one-page guide, so that we answer the first questions fast. P8 (3) As the IT manager I want the old server read-only for 30 days, then off, so that we can roll back. - Definition of Done: code/config in Git · peer-reviewed · acceptance criteria tested · backup covered · documentation updated · the Product Owner accepted it · no open critical security finding.
- Sprint 1 goal: "Finance works on the cloud share, safely." Sprint backlog: P1 (5) + P2 (3) + P3 (5) = 13 points.
- Daily stand-ups: Day 3 impediment — the cloud subscription lacks storage quota; the Scrum Master gets the quota raised by the cloud owner the same day.
- Review: P1 and P2 are Done; P3 is 90 % (two users cannot save Excel files due to a lock setting) → not Done, back to the backlog with a new bug story. Stakeholders see the live finance share and the permission table. New item: "Large CAD files sync slowly — test a sync client".
- Retro: start — pair on permission checks; stop — starting big copies during work hours; continue — daily checksum report. Action: Admin 2 schedules all copies after 20:00 from sprint 2.